Eastman School of Music
A 50,000-square-foot downtown architectural wonder that required 4,000 pieces of steel to be fabricated and delivered on a tightly-managed schedule.
Location
Project Summary
The challenge in fabricating and erecting 380 tons of structural steel for this 50,000-square-foot downtown architectural wonder was that there was no room for staging. Therefore, 4,000 pieces of steel were fabricated and delivered on a tightly-managed schedule with no room for error.
Bottom line: a challenging project involving a nearly 100-foot curved wall was completed on time and on budget despite the tight space.
Project Map
Related Projects

Eugenio Maria de Hostos Charter School -Part 2
As part of the school’s expansion, the two-story addition is planned to provide additional classrooms and office space.

University of Rochester, Joseph P. Mack Catholic Center
This 8,800 sq. ft. facility will stand as a lasting campus landmark, and our team’s precision steel fabrication ensures it’s built for both beauty and long-term durability.